7/11/2024 Construction Update for Mill & 6th Street in Zumbrota, MN
Upcoming schedule:
Work on 6th Street
Work on Mill Street
Traffic Pattern Starting 7-3-24 shown above.
Work on 6th Street
- Starting Monday (7-15-24) sanitary sewer and watermain will be installed between the alley and Warren Avenue.
- Alley access from 6th street will be closed starting Monday (7-15-24)
- Access through the Warren and 6th Street intersection will be closed starting Tuesday (7-15-24) while utilities are being installed. The plan is to have access across the intersection by the weekend. Residents should plan on parking on side streets during this time.
Work on Mill Street
- Sanitary sewer and watermain will be installed on Mill Street between Central Avenue and Jefferson Drive.
- Storm sewer will be completed at the Central Avenue intersection.
Traffic Pattern Starting 7-3-24 shown above.