8/29/2024 Construction Update for Mill & 6th Street
Upcoming schedule:
Work on 6th Street
Work in the alley between Warren Ave and Central Ave
Work on Mill Street
Work on 6th Street
- Sanitary sewer and watermain will continue to be installed working west.
- Access through the Warren and 6th Street intersection will be closed starting Tuesday (9-3-24). The plan is to have access across the intersection by the following weekend. Residents should plan on parking on side streets during this time.
Work in the alley between Warren Ave and Central Ave
- Road will be graded and rocked.
Work on Mill Street
- Blacktop paving is expected to be completed on Friday.
- Access to Cougar Care and the Primary School should come from Jefferson Drive on Thursday and Friday this week.
- Blacktop pavement can be driven on hours after placed and will be cool enough to walk or bike on the next day.
No restrictions to any of the school entrances is expected by Tuesday 9-3.
Concrete sidewalk and concrete driveways will continue up 6th Street up to Central Avenue. Residents will be unable to use their driveways for 7 days after driveway concrete is poured and should plan accordingly.
Updates are available on the "GoZumbrota' app, City Website, and Email. To be added to the email distribution list please email mraasch@ci.zumbrota.mn.us with subject line "Mill & 6th Update"
Project schedule is weather dependent and subject to change.