6-10-2024 Construction Update for Mill & 6th Street in Zumbrota, MN
Upcoming schedule:
Work on 6th Street
Install sanitary sewer and watermain from Central Avenue to the alley between Central Avenue and Warren Avenue.
Road construction from Mill Street to Central Avenue.
Work on Mill Street
Temporary water lines will be placed and tested along Mill Street. Affected properties will have their water service switched to the temporary lines.
Sanitary sewer and watermain will be installed on Mill Street between Central Avenue and 6th Street.
Storm sewer will be installed on Mill Street between Central Avenue and 6th Street.
Access to Central Avenue will switch from Mill street to 6th Street as work progresses.
Current Traffic Pattern For this week shown above:
Work on 6th Street
Install sanitary sewer and watermain from Central Avenue to the alley between Central Avenue and Warren Avenue.
Road construction from Mill Street to Central Avenue.
Work on Mill Street
Temporary water lines will be placed and tested along Mill Street. Affected properties will have their water service switched to the temporary lines.
Sanitary sewer and watermain will be installed on Mill Street between Central Avenue and 6th Street.
Storm sewer will be installed on Mill Street between Central Avenue and 6th Street.
Access to Central Avenue will switch from Mill street to 6th Street as work progresses.
Current Traffic Pattern For this week shown above: