8/9/2024 Construction Update for Mill & 6th Street in Zumbrota, MN

Upcoming schedule:

Work on 6th Street

  • Watermain will be installation between Central Avenue and Warren Avenue.
  • Work in the alley between Warren Ave and Central Ave
  • Starting Monday (8-12-24) sanitary sewer and watermain will be installed. Residents should plan to have no alley access until this work is completed.

 Work on Mill Street

  • Road will be rocked and opened to local traffic.
  • Residents will be switched off temporary water.

Concrete curb & gutter and concrete driveways scheduled to start Wednesday 8-14-24 for all of Mill Street and 6th Street between Mill Street and Central Avenue.  Residents will be unable to use their driveways for 7 days after driveway concrete is poured and should plan accordingly.

Updates are available on the "GoZumbrota' app, City Website, and Email.  To be added to the email distribution list please email mraasch@ci.zumbrota.mn.us with subject line "Mill & 6th Update"

Project schedule is weather dependent and subject to change.

City Hall

175 West Avenue
Zumbrota, MN 55992

Contact Us

Phone: 507-732-7318
Fax: 507-732-7884

Office Hours

Mon - Wed: 7am - 4:30pm
Thurs: 7am - 5:30pm
Fri: 7am - Noon
2023 © Official Website of the City of Zumbrota, MN
Government Websites By Catalis