9/9/2024 Construction Update for East 9th Street
Upcoming schedule:
- Traffic from Anthony Court will be switched to Jefferson Drive. The switchover will occur on Tuesday or later in the week.
- 9th Street will be closed at Dorthea Drive and the north project limits.
- Project-wide storm sewer installation and sanitary sewer installation on 9th Street will begin.
- Road construction will continue between Jefferson Drive, 9th Street, and 460th Street.
Updates are available on the "GoZumbrota' app, City Website, and Email. To be added to the email distribution list please email mraasch@ci.zumbrota.mn.us with subject line "East 9th Street Update"
Project schedule is weather dependent and subject to change.
Traffic Pattern Starting on Tuesday 9-10-24 (shown above:)